Lagos Courts 22 Investors to Secure 2,000MW Power Deals as State Targets Improved Electricity Supply by March 2027
The Lagos State Government is engaging approximately 22 investors to secure new energy-sector investments and expand electricity supply, as it targets an additional 2,000 megawatts of power by March 2027.
The initiative forms part of the state’s efforts to address its longstanding electricity deficit and reduce the dependence of businesses and households on expensive alternative sources of power.
Biodun Ogunleye, Lagos State Commissioner for Energy and Mineral Resources, disclosed the discussions at the Lagos Energy Summit 2026, explaining that the government was working to close investment and contractual gaps that have continued to affect electricity supply.
The discussions with investors are taking place alongside efforts to resolve outstanding issues surrounding power purchase agreements with federal authorities.
These agreements are important because they establish the commercial arrangements under which electricity is purchased and supplied. Resolving outstanding contractual issues could therefore help create greater certainty for investors considering projects in generation, distribution and other parts of the electricity value chain.
The scale of Lagos State’s electricity demand illustrates the challenge facing the government.
Ibilola Kasunmu, Permanent Secretary at the Ministry of Energy and Mineral Resources, said Lagos has an estimated population of 22 million people and electricity demand of approximately 6,000 megawatts.
However, the state receives less than 1,000 megawatts from the national grid, leaving a substantial gap between the electricity available through the grid and the estimated demand of households and businesses.
The difference has encouraged widespread reliance on private electricity generation, including diesel generators, petrol generators, embedded power projects and solar systems.
For businesses, particularly manufacturers, hotels, shopping centres and other energy-intensive operators, the cost of generating electricity independently represents a major component of operating expenditure.
The government’s target of adding 2,000MW by March 2027 would therefore represent a substantial improvement if the proposed investments translate into operational capacity and reliable electricity delivery.
However, the target should be distinguished from electricity already generated or delivered. Discussions with 22 investors indicate an effort to mobilise capital, but they do not establish that all the proposed projects have reached financial close, secured regulatory approvals or begun construction.
The state will also need to address the commercial and infrastructure conditions required to make additional generation useful to consumers.
Electricity projects require more than generating capacity. Investors must have confidence in the ability to sell power, collect payments and operate under predictable regulatory and contractual arrangements.
Transmission and distribution infrastructure must also be capable of moving electricity from generating facilities to the businesses and households that need it.
Lagos has additional opportunities under Nigeria’s evolving electricity market framework, which gives states greater room to develop and regulate electricity markets within their jurisdictions, subject to constitutional and regulatory requirements.
This creates opportunities for state-level power projects, embedded generation and alternative supply arrangements that can respond more directly to local demand.
For investors, Lagos offers a large concentration of commercial and industrial electricity consumers, creating potential demand for independent power generation, renewable energy, gas-fired plants, battery storage and electricity distribution infrastructure.
Nevertheless, the ability to convert that demand into bankable projects will depend on tariffs, payment security, licensing, access to gas and the reliability of the distribution network.
If the state succeeds in resolving the outstanding power purchase agreement issues and attracting the required investment, the projects could reduce the cost of self-generation, improve business productivity and strengthen the competitiveness of Lagos as Nigeria’s commercial centre.
The engagement with 22 investors is therefore an important step towards addressing the state’s electricity deficit, but the key measure of progress will be the amount of additional power that becomes operational and reaches consumers by the March 2027 target.